Run the night crushing shift and build the road base stockpile
You are the control room operator on the Wattle Creek night crushing shift.
What has happened
From 14 September 2026 the Wattle Creek plant runs a night crushing shift to fill a Hunter Roads Consortium order for 20 millimetre aggregate and road base. Conveyor CV03 has returned to service after its guard was refitted. The road base stockpile must be built and blended to specification, samples must be taken at the intervals on the quality plan, and the crusher must stay within its limits. The environmental authority restricts night noise and dust, and the crusher sprays and the stockpile shaping are part of the trigger action response plan. Any plant alarm, guard problem or dust exceedance must be recorded and reported to the Processing Superintendent.
Deliverables
- Start-up check record
- Sample results and stockpile blending record
- Hazard and Incident Register entries for the alarm and dust event
- Shift report for the Processing Superintendent
Documents to use
- Environmental Policy Policy
- Isolation and Permit to Work Procedure Procedure
- Take 5 and Job Hazard Analysis Procedure Procedure
- Health and Safety Policy Policy
Systems to use
Mobile Plant and Prestart Register
The fleet list with each machine's prestart inspections, defects, service status and whether it is available for operation.
Permit to Work and Isolation Register
Permits for isolation, confined space, hot work, working at heights and excavation, with the isolations applied, the crew and the permit status.
Hazard and Incident Register
The register of hazards, near misses, high potential incidents, injuries, environmental events and complaints with investigation status and corrective actions.
Units of competency
Current on training.gov.au for the Resources and Infrastructure Industry Training Package as at 10 September 2026.
RIIPRO301DConduct crushing and screening plant operationsRIIPRO302DPerform process control room operationsRIISRM303EMove and position materials to form stockpilesRIIQUA201EMaintain and monitor site quality standardsQualifications
RII30420Certificate III in Resource ProcessingRII20520Certificate II in Resource ProcessingWhat to look for
Evidence guide
Look for start-up checks that confirm guarding and open permits before the plant runs, samples taken at the required intervals with results recorded, a stockpile method that produces the specified grading, and a correct response to the crusher alarm and the dust trigger, with each recorded and reported to the superintendent.