Plan the excavation across the gas main at chainage 262
You are the leading hand on the Elm Street drainage crew.
What has happened
Work order WO-2026-118 for Wattle Shire Council is a 90 metre stormwater drainage replacement on Elm Street. On Friday 11 September 2026 the trench reaches the gas main crossing at chainage 262. The service plans and the locator survey are on the work order, the main has been potholed by vacuum excavation, and an excavation permit is issued for a 2.1 metre deep trench with a trench shield. The asset owner's conditions require hand or vacuum excavation within the no-go zone and their attendance for any work within 500 millimetres of the main. The company has had no service strikes in twelve months.
Deliverables
- No-go zone and excavation method plan
- Completed Job Hazard Analysis Form
- Updated excavation permit
- Service strike response steps
Documents to use
Systems to use
Project and Drilling Work Orders
Work orders for civil projects and drilling programs with the client, scope, plans and permits attached, crew and progress.
Permit to Work and Isolation Register
Permits for isolation, confined space, hot work, working at heights and excavation, with the isolations applied, the crew and the permit status.
Hazard and Incident Register
The register of hazards, near misses, high potential incidents, injuries, environmental events and complaints with investigation status and corrective actions.
Units of competency
Current on training.gov.au for the Resources and Infrastructure Industry Training Package as at 10 September 2026.
RIICCM202Identify, locate and protect underground servicesRIICCM203ERead and interpret plans and job specificationsRIICCM210Install trench supportRIIWHS302Implement traffic management plansRIIMPO320Conduct civil construction excavator operationsQualifications
RII30926Certificate III in Civil ConstructionRII20720Certificate II in Civil ConstructionWhat to look for
Evidence guide
The plan must treat the service plans as indicative, apply the no-go zone correctly, use non-destructive methods inside it and keep a spotter on mechanical excavation. Look for the asset owner's conditions carried into the permit and the job hazard analysis, a trench shield used for the 2.1 metre depth, and a strike response that stops, isolates, calls and records.